KEEP UP WITH WHAT’S HAPPENING DURING RENOVATION
Click on any photo for enlargement. Scroll down for earlier months.
Apr 2023

Mar 2023

Jan 2023

Dec 2022

Nov 2022

Oct 2022

Sept 2022

August
July 2022
June 2022


May 2022
April 2022
Mar 2022
Feb 2022
Final demolition of the coatroom and lobby restroom.
The darker wall section was the closet west wall.
The beige wall was the restroom.
Construction of the elevator shaft from the perspective of the lobby level
From the size of the construction man, you can get a sense of the size and depth
Wall cut for the stair door
Looking down into the new north stairway. The giant saw blade was used to cut a new door opening in the existing foundation wall. This is how one will access the new fire stair from the Kids City nursery area.
You can see the piece that was cut out laying on the ground, dropped onto an old tire to cushion the blow. It also allows for chains the be wrapped on the 3’ wide x 7’ long by 18” thick hunk of concrete so it can be lifted out of the hole. It weighs about 4,700 pounds.
Jan 2022
Looking northeast from the far corner of our biggest classroom
New wall is for the south wall of a classroom
Very left edge, the frame for the hallway
Facing north, third floor classroom framing & drywall
Right door frame is leading to a new hallway
Way far right, through the framing, are classrooms.
Footing near portico, looking toward Fellowship Hall.
Cinder block in the back left was a Fellowship Hall far northwest window
Framing in front of it is for new stairwell
Lobby, looking from the coffee bar, to the front doors
Right, partition wall going up (temporarily) to block off construction





04-072122-electrical-5.jpg
03-072122-electrical-4
08-Existing-power-entrance-removed
07-ComEd-on-the-job-removing-existing-power-lines
05-072122-electrical-6
09-First-Column-Cover-going-on
10-framing-around-window-for-drywall-072122-480×640-1
14-july-2022-concrete-in-progress-at-HC-pakring-area
12-July-2022-concete-wal-and-window-framing3
13-july-2022-concrete-and-window-framing
15-july-2022-Concrete-walk-and-window-framing-2
16-july-2022-placing-concrete-walk-from-york-rd-to-main-entry
18-July-2022-Steve-and-Luis-on-the-job-as-always-working-on-the-front-canopy
19-july-2022-working-concrete-walk-at-new-north-stair.
21-lobby-work
22-Looking-up-stairs-from-kids-city-to-new-_atrium_-lobby
23-main-lobby-looking-north-from-new-coffee-area-location
26-second-northwast-column-cover-going-in-with-white-frames-partially-attached
27-view-from-main-lobby-out-to-atrium-lobby
29-elevator-components-delivered-ready-to-be-installed-in-shaft-beyond
30-elevator-components-staged-in-new-lobby-and-ready-for-installation
31-new-lobby-buzzing-with-activity
32-placing-concrete-at-new-stair-from-atrium-lobby-to-main-lobby
33-TK-Elevator-at-work-deliveing-and-installing
Main office: new paint and carpeting
June-2022-Freshly-painted-portico-in-progress
June-2022-Looking-into-new-coat-room-from-lobby-former-ladies-restroom
June-2022-New-north-exit-stairs-and-stairs-to-balcony
June-2022-freshly-cut-opening-sawn-into-concrete-wall-to-new-ground-floor-mechanical-room
June-2022-new-wider-opening-to-upper-level-classroom-area
June-2022-curb-forming-in-place-1
June-2022-refreshed-office-new-paint-carpet-and-furnishings


Women’s room demolition



































































